Absolute Mapping
The way Acumen Risk assigns risk impact across multiple activities depends on whether or not you use absolute mapping.
Example of Spreading Risk vs Allocating Total Risk to Multiple Activities
You have the following activities:
Activity | Remaining Duration |
---|---|
Activity A | 17d |
Activity B | 65d |
You map a high probability risk with a very high schedule impact to Activity A. In the Risk Matrix Template, Very High Impact is set to 120-150 days.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 120d | 150d |
If you map that same risk to Activity B, the risk impact is spread over the two activities.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 25d | 31d |
Activity B | 65d | 95d | 119d |
If you map the risk to multiple activities and click the Absolute Mapping option next to the risk, the entire risk impact is allocated to each activity.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 120d | 150d |
Activity B | 65d | 120d | 150d |